How to Recover Retention Sums in Malaysian Construction Projects
Retention is one of the most common reasons contractors find themselves chasing money long after the work is finished. A portion of every payment is held back as security, and getting it released can be surprisingly difficult. For many contractors, retention represents a meaningful slice of their profit on a project. This guide explains how retention works in Malaysia and how to recover what you are owed.
What retention is
Retention is a percentage of the contract sum that the employer withholds from payments to the contractor. It acts as security, giving the employer comfort that the contractor will complete the work properly and return to rectify any defects.
Typically, retention is deducted from each interim payment up to an agreed limit. It is then released in stages, with part usually released at practical completion and the balance released at the end of the defects liability period, once any defects have been made good.
Why retention causes problems
In theory, retention is straightforward. In practice, it is a frequent source of dispute. Employers sometimes delay releasing retention well beyond the point at which it is due, citing alleged defects, ongoing disagreements, or simply their own cash-flow difficulties.
Because retention is released at the back end of a project, it is also vulnerable to being forgotten or deprioritised. The contractor has often moved on to other work, and the sums, while significant in aggregate, may be small relative to the original contract value. This makes it easy for release to slip.
Knowing when your retention is due
The first step to recovering retention is understanding exactly when each portion becomes due under your contract. The contract sets out the triggers for release, usually tied to practical completion and the expiry of the defects liability period.
Keeping track of these milestones is essential. Once a release date has passed and any conditions, such as the making good of defects, have been satisfied, the retention is due and you are entitled to claim it.
Steps to recover retention
If retention is overdue, the approach is similar to recovering any unpaid sum. Start by making a clear, documented demand for the amount due, identifying the basis for release under the contract. Often this prompts payment, particularly where the employer simply needs reminding.
If the demand does not work, retention can form the subject of a payment claim under CIPAA. Because retention is money due under the construction contract, an unpaid retention sum can be referred to adjudication, giving you a fast, binding route to recovery. This is a powerful option that many contractors do not realise is available to them.
Defending against unjustified withholding
Employers sometimes try to justify withholding retention by pointing to alleged defects. Where genuine defects exist and fall within the contractor’s responsibility, the employer may have grounds to retain funds pending rectification. But where the alleged defects are exaggerated, unfounded, or being used as a pretext to delay payment, the contractor can challenge the withholding.
The key is evidence. Records showing that the work was completed properly, that defects were rectified, and that the conditions for release have been met all strengthen your claim and undermine any attempt to withhold the money without justification.
Do not leave money on the table
Retention is your money, held only as security. Once the contractual conditions for release are met, you are entitled to it. Tracking your release dates, demanding payment promptly, and using CIPAA where necessary can turn forgotten retention into recovered cash.
| FREQUENTLY ASKED QUESTIONS When should retention be released? Retention is usually released in stages set by the contract, commonly with part released at practical completion and the balance released at the end of the defects liability period, once any defects have been made good. Can I use CIPAA to recover retention? Yes. Retention is money due under the construction contract, so an overdue retention sum can be the subject of a payment claim and, if necessary, referred to adjudication under CIPAA. Can an employer withhold retention because of defects? Where genuine defects fall within the contractor’s responsibility, an employer may have grounds to retain funds pending rectification. However, withholding based on exaggerated or unfounded defects can be challenged, particularly where the conditions for release have been met. |
| Dealing with this on a live project? Speak to NZSK’s construction law team. Call or WhatsApp +60 16-557 4789 · [email protected] |

