Liquidated Damages in Construction Contracts: A Malaysian Guide

← Back to Legal Blog Construction

Liquidated Damages in Construction Contracts: A Malaysian Guide

When a construction project runs past its completion date, the contract often allows the employer to charge liquidated damages, a pre-agreed sum payable for each day or week of delay. For contractors, liquidated damages can quickly add up to a significant figure, so understanding how they work, and when they can be challenged, is essential. This guide explains liquidated damages in the Malaysian context.

What liquidated damages are

Liquidated damages, sometimes shortened to LD or LAD, are a sum specified in the contract that becomes payable if the contractor fails to complete the works by the agreed date. Instead of the employer having to prove the actual loss caused by the delay, the parties agree in advance on a fixed rate, for example a set amount per day of delay.

The purpose is certainty. Both sides know from the outset what the consequence of late completion will be, which avoids arguments about the precise loss suffered.

Why they are used

Liquidated damages serve a practical function. Delay on a construction project can cause real loss to an employer, such as lost rental income, holding costs, or knock-on disruption. Proving these losses precisely can be difficult and expensive, so a pre-agreed rate provides a straightforward mechanism that both parties can plan around.

For contractors, the existence of a liquidated damages clause is a strong incentive to complete on time and to protect their position through valid extensions of time where delays are not their fault.

The crucial link to extension of time

Liquidated damages and extension of time are closely connected. Liquidated damages generally run from the completion date. If a contractor secures an extension of time for delays that are not their fault, the completion date moves and damages do not accrue for that extended period.

This is why pursuing valid extension of time claims is so important. A contractor who fails to secure an extension they were entitled to may end up paying damages for delays that were never their responsibility. The two issues should always be considered together.

When liquidated damages can be challenged

Liquidated damages are not always beyond challenge. A contractor may dispute them on several bases, for example by establishing an entitlement to an extension of time that reduces or eliminates the period of delay, or by arguing that the employer caused or contributed to the delay.

The way liquidated damages clauses are assessed has also developed through case law in Malaysia, and the precise approach to enforceability and proof of loss can be a matter of legal argument. Because this is a technical area, a contractor facing a substantial liquidated damages claim should take advice rather than simply accepting the deduction.

Practical steps for contractors

The best protection against liquidated damages is proactive project management. Complete on time where you can, and where delays arise that are not your fault, give prompt notice and pursue extensions of time with proper supporting records. Keep clear documentation of the causes of any delay.

If liquidated damages are deducted from your payment, do not assume the deduction is automatically valid. Review the basis for it, consider whether you have an extension of time entitlement, and take advice on whether the deduction can be disputed, potentially through a payment claim and adjudication under CIPAA.

FREQUENTLY ASKED QUESTIONS

What are liquidated damages in construction?
Liquidated damages are a pre-agreed sum specified in the contract that the contractor must pay if the works are completed late. They provide certainty by fixing the consequence of delay in advance, rather than requiring the employer to prove actual loss.

Can liquidated damages be challenged in Malaysia?
Yes. A contractor may challenge liquidated damages on various grounds, including an entitlement to an extension of time or where the employer caused the delay. The enforceability of such clauses can also be a matter of legal argument, so advice is recommended.

How are liquidated damages connected to extension of time?
They are directly linked. Liquidated damages generally run from the completion date, so a valid extension of time that moves that date can reduce or eliminate the damages for the extended period.
Dealing with this on a live project? Speak to NZSK’s construction law team.
Call or WhatsApp +60 16-557 4789      ·      [email protected]
Welcome to Messrs. Ng,Zainurul, Seke & Khoo (NZSK), CLICK to Whatsapp with respective lawyer in charge and we will get back to you as soon as possible! Thank You!
//
Contact Lawyer (NZSK)
Divorce, Industrial & Employment, Corporate Dispute, Construction Dispute, Debt Recovery, Probate & letter administration & etc
Contact Lawyer 咨询律师