The Power of Section 35 CIPAA: Voiding Conditional Payment Clauses in Malaysian Construction Contracts

The Power of Section 35 CIPAA:
Voiding Conditional Payment Clauses in Malaysian Construction Contracts

The Power of Section 35 CIPAA:
Voiding Conditional Payment Clauses in Malaysian Construction Contracts

In Malaysia’s construction industry, where delayed payments are all too common, contractual clauses like “pay-when-paid” or “back-to-back” payment terms have historically placed subcontractors and suppliers at a disadvantage. These clauses allowed main contractors to delay or withhold payments until they themselves were paid by the project owner or developer, creating a dangerous bottleneck in the construction supply chain. Recognizing the unfairness of such provisions, the Malaysian Parliament embedded a powerful provision into the Construction Industry Payment and Adjudication Act 2012 (CIPAA) — Section 35, which renders conditional payment clauses void. This article explores the intent, interpretation, and real-world impact of Section 35, including how courts have applied it and what contractors need to know when entering into or enforcing construction contracts in Malaysia.

Section 35 of CIPAA is a game-changing provision that directly addresses conditional payment mechanisms in construction contracts. It clearly states that any clause making payment contingent upon the payer receiving payment from a third party is void and unenforceable. The objective behind this section is to protect the rights of parties lower in the contractual hierarchy — typically subcontractors and suppliers — who often bear the financial brunt of delayed upstream payments. The drafters of CIPAA recognized that such clauses compromise cash flow, threaten project delivery, and unfairly transfer payment risk from stronger parties to weaker ones.

One of the most significant early interpretations of Section 35 came in the Federal Court case of View Esteem Sdn Bhd v Bina Puri Holdings Bhd [2018]. In this case, the contractor tried to rely on a clause that required payment to be made only after it had received corresponding payments from the project employer. The court held that this “pay-when-paid” clause was void under Section 35, affirming that main contractors cannot withhold payment to subcontractors on the basis of non-payment by a third party. The ruling not only enforced the letter of the law but also strengthened the public policy behind CIPAA — which is to ensure that money flows downstream efficiently and fairly.

In another important decision, Khairi Consult v GJ Runding [2020], the High Court dealt with a consultancy agreement that similarly attempted to tie payment obligations to a third party’s actions. The court again held that such provisions contravened Section 35 and were therefore void. This judgment confirmed that Section 35 is not confined to construction works contracts alone but also applies to consultancy service agreements, including architects, engineers, and quantity surveyors. The broad application of this provision ensures that all stakeholders in the construction ecosystem are protected against delayed payments based on upstream conditions.

However, not all payment-related clauses are necessarily void under Section 35. Courts have acknowledged that the precise wording of a clause matters and that not every reference to certification or third-party action qualifies as a “conditional payment clause.” For example, in Binastra Ablebuild Sdn Bhd v JPS Holdings Sdn Bhd [2019], the court distinguished between a clause that simply required a certificate of payment as a basis for progress billing and one that postponed payment entirely until a specific event occurred. If a clause merely regulates when a payment application can be made (e.g., upon certification), it may be valid. But if it effectively delays the obligation to pay until a condition is met, such as payment by an employer or client, then it risks being voided under Section 35. This subtle distinction is critical and requires parties to review contract wording carefully.

Section 35 has had a transformative impact on contract drafting in the Malaysian construction sector. Since its enforcement, legal advisors and contract administrators have begun eliminating back-to-back clauses or restructuring them to comply with CIPAA. In practice, this means that contractors can no longer hide behind phrases like “subject to payment from the employer” when justifying delays to subcontractor payments. It also incentivizes main contractors to manage their cash flow responsibly and to factor in payment obligations independent of upstream delays.

From a risk management standpoint, Section 35 has reduced one of the major legal uncertainties for subcontractors and consultants. Previously, even if they had completed their work on time and in full, they could still face indefinite delays in payment due to events entirely beyond their control. Now, they have statutory grounds to demand timely payment and can initiate adjudication under CIPAA if the contract party fails to comply. This not only restores balance in contractual relationships but also boosts confidence in the legal system among industry players.

For main contractors, Section 35 presents both a challenge and an opportunity. On the one hand, they can no longer rely on employer delays as a reason for non-payment; on the other hand, they can use the same principle to demand that employers fulfill their payment obligations in a timely manner. In this way, the entire industry benefits from clearer rules and more equitable enforcement.

Despite its strength, Section 35 does not eliminate all payment-related disputes. There have been attempts by some parties to disguise conditional payment clauses by using complex or ambiguous language. However, Malaysian courts have shown a consistent willingness to look beyond the wording and evaluate the substance of the clause. If a clause results in a situation where a party cannot get paid unless someone else pays first, courts are likely to declare it void. This judicial consistency ensures that Section 35 is not just a symbolic safeguard but a real and enforceable one.

In conclusion, Section 35 of CIPAA is one of the most powerful tools available to protect the cash flow of subcontractors, consultants, and smaller players in Malaysia’s construction sector. By rendering conditional payment clauses void, it eliminates a major source of financial injustice and promotes fairness in commercial dealings. Contractors, suppliers, and project owners alike must understand the scope and application of this provision. Whether you are drafting a new contract or enforcing an existing one, careful legal review is essential to ensure compliance with CIPAA and avoid unenforceable terms. In the ever-evolving legal landscape of construction law, Section 35 stands as a testament to the power of legislation in correcting systemic imbalance and ensuring timely payment throughout the industry.

0

error: Content is protected !!
Welcome to Messrs. Ng,Zainurul, Seke & Khoo (NZSK), CLICK to Whatsapp with respective lawyer in charge and we will get back to you as soon as possible! Thank You!
//
Contact Lawyer (NZSK)
Divorce, Industrial & Employment, Corporate Dispute, Construction Dispute, Debt Recovery, Probate & letter administration & etc
Contact Lawyer 咨询律师