CIPAA adjudication is the fastest and most cost-effective way for contractors, subcontractors, and consultants to recover unpaid amounts under Malaysian construction contracts. The Construction Industry Payment and Adjudication Act 2012 (CIPAA) provides a statutory adjudication mechanism that delivers a binding, enforceable decision — equivalent to a court judgment — in approximately 100 working days from the service of the Payment Claim. For an industry where cash flow is existential, this speed is critical.
At NZSK, our construction lawyers in Kuala Lumpur and Selangor handle CIPAA adjudications from both sides — acting for claimants pursuing unpaid payment claims and for respondents defending adjudication proceedings. With offices in Mont Kiara, KL and Puchong, Selangor, we have extensive experience in the CIPAA process before the AIAC and in the enforcement and challenge of adjudication decisions in the Construction Courts.
Why Choose Us?


15+ Years
Law Experience

500+ Cases
Matter Handled

400+ Cases
Custody Secured

RM10Mil +
Hidden Assets Uncovered
How CIPAA Adjudication Works in Malaysia
The CIPAA process follows a strict statutory timeline with deadlines at every stage. The key steps are:
- Payment Claim (Section 5 CIPAA) — the claimant serves a written Payment Claim on the respondent, identifying the amount claimed, the basis of the claim, and stating that it is made under CIPAA. The Payment Claim is the foundation of the adjudication — the adjudicator’s jurisdiction is limited to the matters referred to in it
- Payment Response (Section 6 CIPAA) — the respondent must serve a Payment Response within 10 working days of receiving the Payment Claim. The Payment Response may dispute the claim wholly or in part, stating the amount disputed and the reasons. Failure to serve a Payment Response within time is deemed to be a dispute of the entire Payment Claim — but also deprives the respondent of the ability to raise defences not included in the Payment Response
- Notice of Adjudication (Section 8 CIPAA) — if the dispute remains unresolved, the claimant may serve a Notice of Adjudication on the respondent and the AIAC, and must register the adjudication with the AIAC within 7 days
- Appointment of Adjudicator — the adjudicator is appointed by agreement of the parties or, failing agreement within 10 working days of the Notice of Adjudication, by the Director of the AIAC
- Adjudication Claim and Response — the claimant files a detailed Adjudication Claim; the respondent files an Adjudication Response within 10 working days; the claimant may file an Adjudication Reply within 5 working days
- Adjudication Decision (Section 12 CIPAA) — the adjudicator must deliver the decision within 45 working days of the Adjudication Claim — extendable by agreement. The decision is immediately binding and enforceable
'Pay Now, Argue Later' — The Core Principle of CIPAA
CIPAA operates on the ‘pay now, argue later’ principle — the adjudicator’s decision is temporarily binding and must be complied with immediately, even if the losing party intends to challenge it in arbitration or litigation. This prevents the common practice of using disputes as an excuse to withhold payment indefinitely while the matter proceeds through slow final dispute resolution processes.
The adjudication decision can be enforced as a judgment of the High Court. A party that fails to comply may face execution proceedings against its assets. The Federal Court in Likas Bay Precinct Sdn Bhd v Bina Puri Sdn Bhd [2019] 3 MLJ 244 confirmed that an adjudication decision can also be used as the basis for a winding-up petition against a non-paying respondent — providing additional enforcement pressure.
Challenging an Adjudication Decision — Section 15 CIPAA
An adjudication decision may be challenged by application to the High Court under section 15 of CIPAA on the following grounds:
- Fraud or corruption — in relation to the making of the adjudication decision
- Breach of natural justice — including where a party was not given a proper opportunity to present its case or to respond to the other party’s case
- The adjudicator not acting in accordance with CIPAA
- The decision being made in respect of a matter not referred to adjudication
Section 15 challenges are not merits appeals — the court does not re-examine the substantive correctness of the adjudicator’s decision. The grounds are limited, and the threshold for success is high. We advise on whether a section 15 challenge has realistic prospects and on the procedure for such applications in the KL High Court and Shah Alam High Court Construction Courts.
Direct Payment from the Employer — Section 30 CIPAA
Section 30 of CIPAA provides one of the most powerful tools available to subcontractors: where a subcontractor has obtained an adjudication decision in its favour against the main contractor, but the main contractor fails to pay, the subcontractor may request direct payment from the employer — provided that money is due and payable from the employer to the main contractor. This mechanism allows subcontractors to bypass an insolvent or non-complying main contractor and recover directly from the employer.
CIPAA Adjudication — How We Have Helped
Anonymised examples. Details modified to protect client confidentiality.
Subcontractor | Variation Claims | CIPAA Adjudication | Full Award
| The Situation
A specialist subcontractor in the civil engineering sector had completed significant variation works instructed by the main contractor — additional earthworks and site preparation not covered by the original subcontract. The main contractor refused to certify or pay for the variation works, claiming they had not been formally instructed in writing as required by the subcontract. The sum in dispute was approximately RM680,000. |
What We Did
We advised on the admissibility of the variation claims despite the absence of formal written instructions — relying on contemporaneous site instructions, WhatsApp communications from the main contractor’s site team, and post-completion conduct evidencing acceptance of the variation works. We prepared a comprehensive Payment Claim and Adjudication Claim that addressed the written instruction issue directly, relying on established case law on the construction of variation clauses and the evidential weight of electronic communications. |
✔ Outcome
The adjudicator awarded the subcontractor the full amount claimed — RM680,000 — accepting that the variation works had been properly instructed and accepted notwithstanding the absence of formal written variation orders. The decision was complied with within the statutory timeline. |
Employer | CIPAA Defence | Defective Works Crossclaim | Award Reduced
| The Situation
An employer received a CIPAA Payment Claim from a contractor for RM2.1 million in unpaid progress certificates on a residential development project. The employer disputed the claim — asserting that significant defects in the completed works had resulted in the contractor being overpaid relative to the actual value of work properly executed, and that the employer had a crossclaim for rectification costs and delay damages that exceeded the amount claimed. |
What We Did
We were instructed immediately on receipt of the Payment Claim. We prepared a Payment Response within the 10-working-day deadline, comprehensively setting out the defects and delay grounds for dispute and the employer’s crossclaims. We engaged a quantity surveyor to prepare a detailed valuation of the defective works and a programme expert to quantify the delay damages, and incorporated both expert assessments into the Adjudication Response. |
✔ Outcome
The adjudicator upheld a substantial portion of the employer’s defects crossclaim, reducing the amount awarded to the contractor from RM2.1 million to RM940,000. The employer’s exposure was reduced by more than half. The remaining dispute on defects and delay damages was referred to arbitration for final determination. |
Frequently Asked Questions
Speak to a Construction Lawyer Now!
- (+60)16-557 4789 | (+60)3-8060 0267
- [email protected]
Consultation by appointment — Mont Kiara, Kuala Lumpur & Puchong, Selangor
Related Topics
Construction Payment Dispute
Construction Litigation
Construction Arbitration
Construction Contract Dispute
