Payment disputes are the most common and the most financially damaging type of construction dispute in Malaysia. Approximately 50 per cent of Malaysian construction projects experience underpayment, late payment, or non-payment — a systemic problem that destroys contractor cash flow, causes project delays, and in serious cases forces solvent businesses into insolvency simply because they cannot sustain the gap between work completed and payment received.
At NZSK, our construction law team in Kuala Lumpur and Selangor acts for contractors, subcontractors, consultants, and employers in the full range of construction payment disputes. We advise on the fastest and most effective route to payment recovery — whether through CIPAA adjudication, arbitration, or High Court litigation — and we act quickly, because in construction, delay in pursuing a payment claim is never neutral.
Why Choose Us?


15+ Years
Law Experience

500+ Cases
Matter Handled

400+ Cases
Custody Secured

RM10Mil +
Hidden Assets Uncovered
Types of Construction Payment Disputes We Handle
- Unpaid progress certificates — where the employer or main contractor certifies work done but fails to pay within the contractual payment period — the most common trigger for CIPAA adjudication in Malaysia
- Undercertification disputes — where the certifier issues payment certificates significantly below the value of work properly executed — either as a tactic to withhold payment or due to a genuine valuation dispute
- Variation and instruction disputes — where additional works instructed by the employer or main contractor are disputed as variations, or where the value of agreed variations is in dispute
- Retention money disputes — disputes over the release of retention money — both the moiety released on practical completion and the final retention released at the end of the defects liability period
- Final account disputes — where the parties cannot agree on the final account at the end of the project — including disputes over the value of omissions, additional works, and adjustments to the contract sum
- Loss and expense claims — claims by contractors for financial loss and expense suffered as a result of employer-caused events — including late access to site, late information, prolongation of the contract period, and disruption to the contractor’s planned programme
- Pay-when-paid and conditional payment clause disputes — including the enforceability of conditional payment clauses following the enactment of section 35 of CIPAA 2012
- Bank guarantee and performance bond disputes — including claims on performance bonds, disputes over the right to call on a bond, and injunctions to restrain unconscionable calls
The CIPAA Route vs Arbitration vs Litigation
For most construction payment disputes in Malaysia, CIPAA adjudication is the fastest first step — delivering a binding, enforceable decision in approximately 100 working days. However, the CIPAA decision is interim: it is ‘temporarily final’ and the underlying dispute may still be determined finally by arbitration or litigation. Most construction contracts contain arbitration clauses that make arbitration the final dispute resolution mechanism.
The choice between CIPAA, arbitration, and litigation depends on the nature of the dispute, the urgency of cash flow recovery, the value at stake, and the ultimate goal of the party seeking advice. We advise on the right combination of mechanisms for each specific situation — often running CIPAA adjudication in parallel with or as a precursor to arbitration or litigation.
Variation Claims — Getting Paid for Extra Work
Variation claims are among the most commonly disputed payment issues in Malaysian construction. Many contracts contain strict provisions requiring variations to be formally instructed in writing and agreed in price before the work is undertaken — provisions that are routinely ignored in practice on live construction sites, where verbal instructions and on-the-spot decisions are the reality.
We advise contractors on how to properly document and claim for variation works — including the evidential weight of site meeting minutes, WhatsApp communications, and employer conduct in accepting completed variation works — and we pursue variation claims through CIPAA adjudication and arbitration where agreement cannot be reached.
Construction Payment — How We Have Helped
Anonymised examples. Details modified to protect client confidentiality.
Main Contractor | Final Account Dispute | Retention Release | CIPAA
| The Situation
A main contractor completed a commercial development project but the employer refused to release the second moiety of retention — approximately RM380,000 — alleging unresolved defects at the end of the defects liability period. The employer’s defects list had been contested throughout the DLP; many items on the list had been resolved but the employer continued to add new items to prevent the retention release. |
What We Did
We advised on the legal position on retention release and the employer’s obligation to act in good faith in administering the defects liability period. We served a Payment Claim for the full retention amount under CIPAA, relying on the contractor’s completion certificate and evidence that the alleged outstanding defects had either been resolved or were not defects attributable to the contractor. We prepared a detailed Adjudication Claim addressing each item on the employer’s defects list with photographic evidence and expert assessment. |
✔ Outcome
The adjudicator awarded the contractor RM320,000 — the full retention less a small amount accepted as relating to a genuine outstanding defect. The employer released the adjudicated amount promptly to avoid enforcement proceedings. The remaining defect item was resolved by negotiation shortly after. |
Frequently Asked Questions
Speak to a Construction Lawyer Now!
- (+60)16-557 4789 | (+60)3-8060 0267
- [email protected]
Consultation by appointment — Mont Kiara, Kuala Lumpur & Puchong, Selangor
Related Topics
CIPAA Adjudication
Construction Litigation
Construction Arbitration
Construction Contract Dispute
